A further 150 metres of vulnerable seawall will be secured with a steel sheet pile wall in the second phase of repairs to Exmouth’s sea defences, planned for late September.

A further 150 metres of vulnerable seawall will be secured with a steel sheet pile wall in the second phase of repairs to Exmouth’s sea defences, planned for late September.

Phase two is projected to cost £1.627million of the estimated full project cost of £3.312million. East Devon District Council (EDDC) has allocated £1.5million to the work, with £1.72million of additional funding from central government.

Since March 2024, engineers have been working hard to put in place permanent measures strengthening Exmouth’s sea defences. A steel sheet pile wall has been installed through the ground and the 90 metres of failed wall, through the nearly completed first phase. This section is where sand levels had dropped below the foundations, causing the wall to fall forward and crack.

After a serious failure to the seawall in 2023, EDDC with their contractors snapped into action with emergency temporary measures taken to protect the damaged wall. Thousands of tons of sand were transferred, and large concrete blocks were put in place only hours before an impending storm. These temporary barriers successfully absorbed the energy of the waves and prevented further much more serious damage. Following the storm, contractors raised sand levels by the seawall and put additional concrete blocks in place.

Minimising disruption to beach users during the busy summer season is important, so on-site engineering work has not been scheduled to take place during the school holidays. In the first phase, contractors have been working on Saturdays too, to complete the project more quickly.

Andrew Hancock, EDDC’s Assistant Director for Streetscene, said:

"Strengthening Exmouth’s coastal defences for the next 100 years is vital, with increasingly frequent, more severe storms an unfortunate consequence of the climate crisis.”

“Securing the seawall ahead of the winter storm season is an urgent task. The council’s engineers are working incredibly hard to ensure the best options are chosen in terms of financial costs and environmental impacts too.”

“EDDC would like to thank visitors, residents, and local businesses for their patience whilst this important work continues.”

Phase two was agreed by EDDC’s cabinet on Wednesday, 5 June 2024. Cabinet also considered historic decisions and reasons why the seawall failed, an issue that will be investigated further by a future Scrutiny committee.

Residents will be consulted on the appearance of the wall. The cladding of the wall and the replacement of a slipway (with full planning permission to be requested in due course), will be the focus of the third phase.

More from Exeter & East Devon News

  • Devon man jailed for terrorism offences

    A 20-year-old man from Honiton, Devon, has today (Thursday 17 April) been sentenced to five-and-a-half years in prison for terrorism offences.

  • Protesters fear for future of Exeter swimming pool

    Around 50 campaigners gathered at the Isca Centre as Exeter City Council held its final public consultation. The Save Northbrook Pool group claims the pool gets less subsidy than others but is only open a third as much for public swimming.

  • Pop-up market proposal for Exeter city centre

    Exeter could soon get a pop-up market on the former bus station site off Sidwell Street. An entrepreneur has proposed the idea, backed by Councillor Lynn Wetenhall, who noted it was the top choice in a recent public consultation.

  • Exeter to lobby Post Office over city centre branch future

    Post Offices at Paignton, Plymouth, Teignmouth and Bideford were on an initial list of 115 branches earmarked for possible closure earlier this year, sparking an outcry.

  • Staff turnover rises as long-term sickness weighs on absences

    East Devon District Council’s personnel committee this week heard that staff turnover had reached 11.5 per cent in the 11 months to the end of February.

  • East Devon goes beyond requirements on care leave

    Workers at a Devon council who have caring responsibilities will get better terms to take time off than legislation requires. East Devon District Council’s personnel committee agreed that staff who are carers would receive five days of leave beyond their standard allowance, as required by the UK Carer’s Leave Act.

  • 200 marathons in 200 days – 65-year-old runs full length of UK coastline

    Steve James, 65, will set off from Topsham, Devon, today, Wednesday (April 16th), supported by his wife and their five children, aiming to return there after seven months of consecutive days of running anticlockwise around the coast.

  • Burglary and fraud, Exeter

    Devon & Cornwall police are investigating a report of burglary and fraud in Exeter and have released pictures of a man and a woman we would like to speak to in connection with the incidents.

On Air Now Kev Parker 7:00pm - 9:00pm
Now Playing
Chance Big Country Download
Recently Played

Schedule

  • Non Stop Pop

    9:00pm - Midnight

    The Music You Love

  • Non Stop Pop

    Midnight - 7:00am

    The Music You Love

  • Ben Clark

    7:00am - 11:00am

    Breakfast with travel updates, news headlines, entertainment.

Today's Weather

  • Exmouth

    Sunny intervals

    High: 13°C | Low: 9°C

  • Exeter

    Heavy rain shower

    High: 15°C | Low: 8°C

  • Dawlish

    Sunny intervals

    High: 13°C | Low: 9°C

  • Torquay

    Sunny intervals

    High: 13°C | Low: 9°C

  • Sidmouth

    Sunny intervals

    High: 14°C | Low: 9°C

Easy Fundraising

What's On